DSA was involved in the construction supervision of the Tirraawarra-Mirramella 8” GRE Crude Oil Flowline Installation in the Cooper Basin.
DSA was engaged to monitor the Installation Contractor and to provide D.5 certified supervisors. Our supervisors found numerous manufacturing defects in the piping product that was procured from an Indonesian manufacturer.
DSA were later engaged to perform pipe testing and review of the product to ensure compliance with API15HR and ISO 14692.
The pipeline was tested to 100 BarG and was designed to be operating at 100°C.